Service notice - Lane Closures for Inspection and Repairs - Fulford Harbour Terminal - November 16-18, 2026
Posted:
Thursday, November 05, 2026
Lane Closures for Inspection and Repairs
Fulford Harbour (Salt Spring Island) Terminal
November 16–18, 2026
To support safe and reliable service, repairs to a section of the timber structure beneath the holding compound at Fulford Harbour terminal will take place from November 16–18, 2026.
Crews will remove sections of asphalt and the underlying decking between lanes 8–11 to allow for inspection and subsequent repairs.
Lanes 8–11 will be temporarily closed, and customers are asked to follow the directions of staff, signage, and traffic control personnel, as vehicle line-ups are expected on Fulford-Ganges Road.
Work will take place during daytime hours, starting at 8 am. Noise due to jackhammering and asphalt removal is expected on Monday, November 16, and may continue into Tuesday, November 17. Minimal noise is anticipated for the remainder of the work, while the inspection and repairs take place.
Updates will be shared through Service Notices if there are any impacts to operations.
Thank you to our customers and neighbours for your patience and understanding as we complete these necessary repairs.
For up-to-date sailing and departure information, check Current Conditions, follow @BCFerries on X, or phone 1-888-223-3779 for further assistance.